Home  |  About Barbara  |  Issues  |  Blog  |  On The Trail  |  Contact Us  | 
COMSTOCK FOR DELEGATE BLOG

Demolition of the Lewinsville Road Bridge
Monday, January 2, 2012

This notice from Virginia MegaProjects addresses the upcoming demolition of the old Lewinsville Road bridge over I-495. A new bridge that opened to traffic on August 19 was constructed to accomodate the future Capital Beltway HOT Lanes. Demolition is scheduled to begin on or about Tuesday, January 3 and will take from three to four weeks to complete, weather permitting. For all nights except Friday, the demolition work will take place between the hours of 11 pm and 4 am. On Friday nights, work will begin at 11 pm and continue until 7 am on Saturday morning.
Lewinsville Road Bridge Fact Sheet








Paid for by Friends of Barbara Comstock.